Project Name: Suncoast Parkway 2, Phase 3

Project Website: https://floridasturnpike.com/turnpike-projects/featured-projects/suncoastparkway2/suncoast-parkway-2-phase-3/

Project Number: 442764-2,-3

Impacted Counties: Citrus

Condemning Authority: Florida's Turnpike Enterprise

Budget for Land Acquisition: $31,000,000

Project Description:

Suncoast Parkway 2, Phase 3 will be approximately ten miles of four-lane toll road from CR 486 to US 19.

The Suncoast Parkway is being constructed in phases. Phase 1, from US 98 to SR 44, opened in February 2022. Phase 2, from SR 44 to CR 486, is expected to open in 2026.

Phase 3 is divided into segments 3A and 3B.

Segment 3A is from CR 486 to CR 495. This segment is in the design phase. Right-of-way acquisition scheduled for 2023 and construction in 2025.

Segment 3B is from CR 495 to US 19. This segment is also in the design phase. Right-of-way acquisition scheduled for 2024 and construction in 2026.

A Public Meeting was held in early March 2023. You can view the presentation here. The presentation video can also be viewed below.

If your property is being impacted by this project, please call us toll-free at (844) 925-3144 for a free review of your case. Harris Harris Bauerle Lopez is a full service firm of skilled eminent domain attorneys who will take your case without taking a single penny out of your pocket. All of our fees and the costs of consultants retained on your behalf are paid by the taking authority over and above what we obtain for your compensation.